Minerals And Mining (Health, Safety And Technical Regulations, 2012) (L.I. 2182)

Regulation 338The manager of a mine shall ensure that(a) a new steam boiler is not used in the mine, unless there has been obtained from the manufacturer of the boiler a certificate that specifies the maximum permissible working pressure of the boiler, and states the nature of the tests to which the boiler and fittings have been subjected; and(b) the certificate is made available for inspection by an inspector, and the boiler is marked in a manner that enables it to be identified as the boiler to which the certificate relates.

Procedures to Follow




Not Avaiable

Responsible Institution

Minerals Commission

36 Second Cantonments Cl, Accra
Email:mlnrinfo@mlnr.gov.gh
Website:http://mincom.gov.gh

Relevant Forms to Download

Not Available

Fees / Charges




Not Avaiable