Regulation 3 Environmental Impact Assessment. No environmental permit shall be issued by the Agency for any of the undertakings mentioned in Schedule 2 to ...

Regulation 5 Initial Assessment by Screening of Application. (1) The Agency shall on receipt of an application and any other relevant information required, ...

Regulation 6 Screening Report After the screening under regulation 5 the Agency shall issue a screening report on the application and shall state in the sc ...

 Regulation 7 Registration and Issue of Environmental Permit. (1) Where the Agency approves an application at the initial assessment, it shall registe ...

Regulation 9 Preliminary Environmental Report (1) Where the Agency upon consideration of an application decides that there is the need for a preliminary en ...

Regulation 10 Environmental Impact Statement. (1) For the purpose of regulation 9(4) the applicant shall submit an environmental impact statement in respec ...

Regulation 11 Scoping Report. A scoping report shall set out the scope or extent of the environmental impact assessment to be carried out by the applicant, ...

Regulation 12 Draft Terms of Reference The draft terms of reference shall stipulate that the environmental impact statement on the proposed undertaking wil ...

Regulation 13 Action on Scoping Report. (1) The Agency shall upon receipt of a scoping report examine it and inform the applicant within 25 days of the rec ...

Regulation 14 Matters to be Addressed in Environmental Impact Statement. (1) In submitting an environmental impact statement pursuant to regulation 13(2), ...

Regulation 16 Consideration and Review of Environmental Impact Statement and Publication of Notices of Environmental Impact Statement. (1) The applicant sh ...

Regulation 17 Public Hearing. (1) The Agency shall hold a public hearing in respect of an application where (a) upon a notice issued under regulation ...

Regulation 18 Review of Environmental Impact Statement after Public Hearing. (1) A draft environmental impact statement shall be further reviewed by the Ag ...

Regulation 19 Finalisation of Environmental Impact Statement and Grant of Environmental Permit. Where an environmental impact statement is acceptable to th ...

Regulation 20 Period for Determination of an Application. (1) Subject to the provisions of these Regulations an application for an environmental permit und ...

Regulation 21 Validity of Environmental Permit. Where an environmental permit is granted to an applicant, the permit shall be valid for a period of 18 mont ...

Regulation 22—Requirement for an Environmental Certificate. (1) Where an undertaking in respect of which a preliminary environmental report or an environ ...

Regulation 23 Funds for Reclamation. An undertaking in respect of which a reclamation plan is required shall be required to post reclamation bond based on ...

Regulation 24 Environmental Management Plan. (1) The person responsible for an undertaking in respect of which a preliminary environmental report or an env ...

Regulation 24 Environmental Management Plan. (1) The person responsible for an undertaking in respect of which a preliminary environmental report or an env ...

Regulation 26 Suspension, Cancellation or Revocation of Permit and Certificates. (1) The Agency may suspend, cancel or revoke an environmental permit or ce ...

SCHEDULE 1 (Regulation 1 (1))   UNDERTAKINGS REQUIRING REGISTRATION AND ENVIRONMENTAL PERMIT.   AGRICULTURAL AND RELATED SERV ...

SCHEDULE 2 (Regulation 3)   UNDERTAKINGS FOR WHICH ENVIRONMENTAL IMPACT ASSESSMENT (EIA) IS MANDATORY 1. Agriculture. (a) land dev ...

SCHEDULE 3 (Regulation 15 (2)) ENVIRONMENTAL IMPACT ASSESSMENT (EIA) SCOPING NOTICE ........................................................ ...